Brownfield assessment projects typically follow a common path. Kalispell will begin inventorying potential sites by meeting with community leaders, the public, and Steering Committee members to identify sites for potential site assessments. Owners of these properties will be contacted to determine whether they would like to voluntarily participate in the assessment program. Site assessments will be completed as sites are identified and deemed eligible for assessment by the EPA, and where the owner has granted access to the property for assessment. Site assessment findings will be used to clear the property of perceived environmental problem(s) or to develop a plan for additional assessment or site cleanup consistent with the redevelopment vision for the site. The schedule below shows the general anticipated timetable for the Kalispell Brownfield project.

Task Approximate Completion Date
Establish Steering Committee June 2010
Begin Meetings with Key Community Contacts June 29, 2010
First Steering Committee Meeting June 30, 2010
First Public Meeting August 4, 2010
Begin Phase I Environmental Site Assessments
  • Meetings with Landowners of Priority Sites
  • Obtain Access to Sites
August/September 2010
Begin Phase II Environmental Site Assessments
  • Preparation of Quality Assurance Project Plan
  • Preparation of Sampling and Analysis Plans
November/December 2010
Second Public Meeting April 2011
Third Public Meeting February 2012
Complete all Brownfield Assessment Activities Spring 2013